“Innovation and Excellence” : Cuddy Update

Left to right: Chad Mencarelli. Project Manager w/LRE;  Brent Scholten, Allegan Maintenance Engineer; Denise Medemar, Allegan Drain Commissioner; Dan Fredricks, VP and Project Designer/Manager w/LRE;  Jim Dull, Barry Drain Commissioner; and Deb Masselink, Rich Beukema, and Greg Purcell of the Friends of the Cuddy Drain  (*)

 

Thursday October 12th, several of us met once again at our beloved Cuddy Drain.  The entire project is being submitted to the Michigan Association of County Drain Commissioners – who will pick one project to win an “Innovation and Excellence Award”!!  Of course, we “Friends of the Cuddy Drain” feel it’s a shoo-in, but it would be nice if our Drain Commissioners were to win this accolade – a lot of time and effort went into it.  For the 3+ years of this project, Denise Medemar, Russ Yarger; and later Jim Dull; have consistently listened to and respected the voices of the residents.  Dan Fredricks designed a plan that finally solved the issues that had plagued Cuddy residents for decades, and his design turned a flood-prone, silt-laden, drain-filled-with-pathogens into the crystal-clear and safe body of water that we see today.  Chad Mencarelli was on-site during the construction, and Brent Scholten keeps everything running smoothly.  The Cuddy residents told the commissioners they were prepared to pay the (admittedly-steep) assessment as long as the “job was done right”.  And it was – all our original remediation goals were met.

All of the above still strikes me as amazing

*Absent from photo: Mark Englerth, Yankee Springs Supervisor who facilitated countless meetings between the Drain Commissioners and the residents, giving everyone a voice in the project.

 

I have to add a PS: on October 14th and overnight into the 15th, we received 6.75″ of rain, twice the amount that triggered the Great Cuddy Flood of 2013.  When I drove past the Cuddy on the 15th, it was happily burbling along.  No flood, no silt, no debris, no drama.

Advertisements